| Sperry Projects - 01/08 | |||||||
| Project # | Coordinator | Start | Finish | Project Name | Phase | Client | % Complete |
| 200667 | Joe Wo | 5/18/2006 8:00 | 8/29/2008 17:00 | Sperry Landscaping | Hold | 0% | |
| 5/18/2006 8:00 | 12/1/2006 17:00 | 1.Design | 0% | ||||
| 5/1/2007 8:00 | 5/1/2007 17:00 | 2.Bid | 0% | ||||
| 8/29/2008 8:00 | 8/29/2008 17:00 | 3.Construction | 0% | ||||
| 200029 | Joe Wo/Rob | 1/1/2002 8:00 | 8/14/2007 17:00 | Sperry Learning Center Abatement | Complete | 99% | |
| 1/1/2002 8:00 | 3/26/2004 17:00 | 1.Design | 100% | ||||
| 12/1/2004 8:00 | 2/1/2005 17:00 | 2.Equipment | 100% | ||||
| 10/3/2005 8:00 | 8/14/2007 17:00 | 3.Construction | 100% | ||||
| 2008040 | Chris | 12/15/2007 8:00 | 1/31/2008 17:00 | Sperry Rm 103 Power Needs for Computer Workstations | Constr | 67% | |
| 12/15/2007 8:00 | 12/17/2007 17:00 | 1.Design | 100% | ||||
| 12/15/2007 8:00 | 12/17/2007 17:00 | 2.Bid | 100% | ||||
| 1/31/2008 8:00 | 1/31/2008 17:00 | 3.Construction | 0% | ||||