| Studio West Projects - 01/08 | |||||||
| Project # | Coordinator | Start | Finish | Project Name | Phase | Client | % Complete |
| 2007061 | Joe We | 6/30/2008 8:00 | 4/30/2010 17:00 | Studio West Addition & Alterations | Planning | 0% | |
| 6/30/2008 8:00 | 6/30/2008 17:00 | 1.Design | 0% | ||||
| 9/15/2008 8:00 | 9/15/2008 17:00 | 2.Bid | 0% | ||||
| 10/1/2008 8:00 | 4/30/2010 17:00 | 3.Construction | 0% | ||||
| 200676 | Joe Wo | 5/18/2006 8:00 | 8/15/2008 17:00 | Studio West EMS & Recommissioning | Hold | 0% | |
| 5/18/2006 8:00 | 11/30/2007 17:00 | 1.Design | 0% | ||||
| 11/30/2007 8:00 | 11/30/2007 17:00 | 2.Bid | 0% | ||||
| 3/3/2008 8:00 | 8/15/2008 17:00 | 3.Construction | 0% | ||||
| 2008015 | Bruce | 9/7/2007 8:00 | 1/22/2008 17:00 | Studio West Maintenance Garage Rehab for Art Dept | Constr | 17% | |
| 9/7/2007 8:00 | 9/7/2007 17:00 | 1.Design | 100% | ||||
| 9/7/2007 8:00 | 9/7/2007 17:00 | 2.Bid | 100% | ||||
| 9/7/2007 8:00 | 1/22/2008 17:00 | 3.Construction | 15% | ||||
| 2008031 | Phil | 3/28/2008 8:00 | 9/1/2008 17:00 | Studio West Rm 131 Technology Classroom Installation | Planning | 0% | |
| 3/28/2008 8:00 | 3/28/2008 17:00 | 1.Design | 0% | ||||
| 5/1/2008 8:00 | 5/1/2008 17:00 | 2.Bid | 0% | ||||
| 9/1/2008 8:00 | 9/1/2008 17:00 | 3.Construction | 0% | ||||