Raquette Lake Projects - 01/08
Project # Coordinator Start Finish Project Name Phase Client % Complete
200512 TBD 3/1/2005 8:00 10/1/2007 17:00 Raquette Lake Antlers/Cedars Cabin Accessibility Hold Jack 25%
    3/1/2005 8:00 9/1/2005 17:00 1.Design     100%
    9/1/2005 8:00 11/22/2005 17:00 2.Bid     50%
    1/2/2006 8:00 10/1/2007 17:00 3.Construction     0%
200791 Bruce 3/7/2007 8:00 10/31/2007 17:00 Raquette Lake Replace Machine Shop Complete   99%
    3/7/2007 8:00 3/7/2007 17:00 1.Design     100%
    3/7/2007 8:00 3/7/2007 17:00 2.Bid     100%
    3/7/2007 8:00 10/31/2007 17:00 3.Construction     100%