| Park Center Projects - 01/08 | |||||||
| Project # | Coordinator | Start | Finish | Project Name | Phase | Client | % Complete |
| 2008046 | Bruce | 1/16/2008 8:00 | 8/15/2008 17:00 | Park Center 1st Floor Classroom Soundproofing | Planning | 0% | |
| 1/16/2008 8:00 | 1/16/2008 17:00 | 1.Design | 0% | ||||
| 1/16/2008 8:00 | 1/16/2008 17:00 | 2.Bid | 0% | ||||
| 8/15/2008 8:00 | 8/15/2008 17:00 | 3.Construction | 0% | ||||
| 2008049 | Chris | 1/16/2008 8:00 | 8/15/2008 17:00 | Park Center 2nd Floor Lobby Lighting | Planning | 0% | |
| 1/16/2008 8:00 | 1/16/2008 17:00 | 1.Design | 0% | ||||
| 1/16/2008 8:00 | 1/16/2008 17:00 | 2.Bid | 0% | ||||
| 8/15/2008 8:00 | 8/15/2008 17:00 | 3.Construction | 0% | ||||
| 200785 | Joe We | 9/3/2007 8:00 | 2/29/2008 17:00 | Park Center Corey Gym Camera Technology | Planning | Joan Sitterly | 55% |
| 9/3/2007 8:00 | 11/30/2007 17:00 | 1.Design | 100% | ||||
| 11/30/2007 8:00 | 1/15/2008 17:00 | 2.Bid | 2% | ||||
| 1/31/2008 8:00 | 2/29/2008 17:00 | 3.Construction | 0% | ||||
| 2008044 | Bruce | 1/16/2008 8:00 | 8/15/2008 17:00 | Park Center Holstein Pool Platforms & Diving Boards | Planning | 0% | |
| 1/16/2008 8:00 | 1/16/2008 17:00 | 1.Design | 0% | ||||
| 1/16/2008 8:00 | 1/16/2008 17:00 | 2.Bid | 0% | ||||
| 8/15/2008 8:00 | 8/15/2008 17:00 | 3.Construction | 0% | ||||
| 200788 | Chris | 3/7/2007 8:00 | 10/19/2007 17:00 | Park Center Poolside Lighting | Complete | Jesse Adams | 100% |
| 3/7/2007 8:00 | 3/7/2007 17:00 | 1.Design | 100% | ||||
| 3/7/2007 8:00 | 3/7/2007 17:00 | 2.Bid | 100% | ||||
| 3/7/2007 8:00 | 10/19/2007 17:00 | 3.Construction | 100% | ||||
| 200765 | Bruce | 2/1/2007 8:00 | 8/24/2007 17:00 | Park Center Refurbish Folding Doors Corey Gym | Punchlist | Joan Sitterly | 99% |
| 2/1/2007 8:00 | 8/15/2007 17:00 | 1.Design | 100% | ||||
| 2/1/2007 8:00 | 8/15/2007 17:00 | 2.Bid | 100% | ||||
| 2/1/2007 8:00 | 8/24/2007 17:00 | 3.Construction | 99% | ||||
| 2007104 | Joe We | 6/1/2007 8:00 | 3/28/2008 17:00 | Park Center Rm 205 Skating Rink Gallery Guardrail Netting | Const | Nasrin | 41% |
| 6/1/2007 8:00 | 8/15/2007 17:00 | 1.Design | 100% | ||||
| 6/1/2007 8:00 | 9/14/2007 17:00 | 2.Bid | 100% | ||||
| 6/1/2007 8:00 | 3/28/2008 17:00 | 3.Construction | 6% | ||||
| 2008041 | Phil | 1/16/2008 8:00 | 8/15/2008 17:00 | Park Center Rm D206 Sink & Cabinet | Planning | 0% | |
| 1/16/2008 8:00 | 1/16/2008 17:00 | 1.Design | 0% | ||||
| 1/16/2008 8:00 | 1/16/2008 17:00 | 2.Bid | 0% | ||||
| 8/15/2008 8:00 | 8/15/2008 17:00 | 3.Construction | 0% | ||||
| 200604 | Phil | 8/1/2005 8:00 | 1/1/2009 17:00 | Park Center Signage Alumni Arena & Other Areas | Design | 0% | |
| 8/1/2005 8:00 | 8/1/2005 17:00 | 1.Design | 100% | ||||
| 8/1/2005 8:00 | 2/29/2008 17:00 | 2.Bid | 0% | ||||
| 8/1/2005 8:00 | 1/1/2009 17:00 | 3.Construction | 0% | ||||