| Old Main Projects - 01/08 | |||||||
| Project # | Coordinator | Start | Finish | Project Name | Phase | Client | % Complete |
| 200643 | Bruce | 5/1/2007 8:00 | 4/30/2008 17:00 | Old Main Art History Card Access | Const | 84% | |
| 5/1/2007 8:00 | 4/30/2008 17:00 | 1.Design | 100% | ||||
| 5/1/2007 8:00 | 5/1/2007 17:00 | 2.Bid | 100% | ||||
| 5/1/2007 8:00 | 1/30/2008 17:00 | 3.Construction | 63% | ||||
| 200783 | Bruce | 3/7/2007 8:00 | 3/28/2008 17:00 | Old Main Basement Display Space Improvement | Planning | Lori Ellis | 14% |
| 3/7/2007 8:00 | 8/30/2007 17:00 | 1.Design | 60% | ||||
| 3/7/2007 8:00 | 9/28/2007 17:00 | 2.Bid | 0% | ||||
| 3/7/2007 8:00 | 3/28/2008 17:00 | 3.Construction | 0% | ||||
| 200799 | Joe We | 6/1/2007 8:00 | 12/31/2008 17:00 | Old Main Fine Arts Program Feasibility | Planning | J. Donovan | 3% |
| 6/1/2007 8:00 | 5/30/2008 17:00 | 1.Design | 8% | ||||
| 6/16/2008 8:00 | 6/16/2008 17:00 | 2.Bid | 0% | ||||
| 6/1/2007 8:00 | 12/31/2008 17:00 | 3.Construction | 0% | ||||
| 200650 | TBD | 5/1/2006 8:00 | 6/1/2007 17:00 | Old Main Ice Pro Maintenance System | Hold | Glenn | 0% |
| 5/1/2006 8:00 | 6/30/2006 17:00 | 1.Design | 0% | ||||
| 5/1/2006 8:00 | 8/1/2006 17:00 | 2.Bid | 0% | ||||
| 5/1/2006 8:00 | 6/1/2007 17:00 | 3.Construction | 0% | ||||
| 200622 | Joe We | 12/1/2006 8:00 | 11/1/2007 17:00 | Old Main Kiln Replacement | Complete | J.Donovan | 87% |
| 2/1/2007 8:00 | 5/1/2007 17:00 | 1.Design | 100% | ||||
| 5/1/2007 8:00 | 6/1/2007 17:00 | 2.Bid | 100% | ||||
| 12/1/2006 8:00 | 11/1/2007 17:00 | 3.Construction | 83% | ||||
| 200744 | Joe Wo | 11/3/2006 8:00 | 8/15/2008 17:00 | Old Main Outdoor Space for Kilns & Sculpture Burnout Kilns | Hold | J.Donovan | 0% |
| 11/3/2006 8:00 | 11/3/2006 17:00 | 1.Design | 0% | ||||
| 11/3/2006 8:00 | 11/3/2006 17:00 | 2.Bid | 0% | ||||
| 11/3/2006 8:00 | 8/15/2008 17:00 | 3.Construction | 0% | ||||
| 2008020 | Bruce | 10/1/2007 8:00 | 7/30/2008 17:00 | Old Main Rm 212 Investigate Air Condition of Space | Design | 0% | |
| 10/1/2007 8:00 | 10/1/2007 17:00 | 1.Design | 0% | ||||
| 10/1/2007 8:00 | 10/1/2007 17:00 | 2.Bid | 0% | ||||
| 10/1/2007 8:00 | 7/30/2008 17:00 | 3.Construction | 0% | ||||
| 2008048 | Bruce | 1/16/2008 8:00 | 8/15/2008 17:00 | Old Main Rm B10 Drawing Room Lights | Planning | 0% | |
| 1/16/2008 8:00 | 1/16/2008 17:00 | 1.Design | 0% | ||||
| 1/16/2008 8:00 | 1/16/2008 17:00 | 2.Bid | 0% | ||||
| 8/15/2008 8:00 | 8/15/2008 17:00 | 3.Construction | 0% | ||||
| 2008021 | Bruce | 10/10/2007 8:00 | 11/1/2007 17:00 | Old Main Rm B10 Install Track Lighting | Hold | 0% | |
| 10/10/2007 8:00 | 10/10/2007 17:00 | 1.Design | 0% | ||||
| 10/10/2007 8:00 | 10/10/2007 17:00 | 2.Bid | 0% | ||||
| 11/1/2007 8:00 | 11/1/2007 17:00 | 3.Construction | 0% | ||||
| 200451 | Joe We | 10/3/2005 8:00 | 8/15/2008 17:00 | Old Main Window Replacement | Constr | 50% | |
| 10/3/2005 8:00 | 10/3/2005 17:00 | 1.Design | 100% | ||||
| 1/9/2006 8:00 | 1/9/2006 17:00 | 2.Bid | 100% | ||||
| 4/2/2007 8:00 | 8/15/2008 17:00 | 3.Construction | 50% | ||||