| Neubig Projects - 01/08 | |||||||
| Project # | Coordinator | Start | Finish | Project Name | Phase | Client | % Complete |
| 200674 | Joe We | 11/15/2006 8:00 | 8/15/2007 17:00 | Neubig Bookstore Renovations | Hold | B.McNamara | 0% |
| 11/15/2006 8:00 | 11/15/2006 17:00 | 1.Design | 15% | ||||
| 11/15/2006 8:00 | 11/15/2006 17:00 | 2.Bid | 0% | ||||
| 11/15/2006 8:00 | 8/15/2007 17:00 | 3.Construction | 0% | ||||
| 200662 | Joe We | 12/1/2006 8:00 | 5/30/2008 17:00 | Neubig Dining Center | Design | 20% | |
| 12/1/2006 8:00 | 2/28/2008 17:00 | 1.Design | 20% | ||||
| 4/30/2008 8:00 | 4/30/2008 17:00 | 2.Bid | 0% | ||||
| 5/30/2008 8:00 | 5/30/2008 17:00 | 3.Construction | 0% | ||||
| 200657 | Joe We | 5/2/2006 8:00 | 8/1/2008 17:00 | Neubig Entrance | Design | 24% | |
| 5/2/2006 8:00 | 11/30/2007 17:00 | 1.Design | 50% | ||||
| 5/2/2006 8:00 | 1/31/2008 17:00 | 2.Bid | 0% | ||||
| 8/1/2008 8:00 | 8/1/2008 17:00 | 3.Construction | 0% | ||||
| 200669 | Joe Wo | 5/18/2006 8:00 | 8/31/2007 17:00 | Neubig Hall Loading Dock Redesign | Hold | Dana Wavle | 17% |
| 5/18/2006 8:00 | 5/18/2006 17:00 | 1.Design | 50% | ||||
| 5/1/2007 8:00 | 5/1/2007 17:00 | 2.Bid | 0% | ||||
| 8/31/2007 8:00 | 8/31/2007 17:00 | 3.Construction | 0% | ||||
| 2008029 | Joe We | 1/16/2008 8:00 | 8/15/2008 17:00 | Neubig Roof Replacement | Planning | 0% | |
| 1/16/2008 8:00 | 1/16/2008 17:00 | 1.Design | 0% | ||||
| 1/16/2008 8:00 | 1/16/2008 17:00 | 2.Bid | 0% | ||||
| 8/15/2008 8:00 | 8/15/2008 17:00 | 3.Construction | 0% | ||||