| Multiple Bldg. Projects - 01/08 | |||||||
| Project # | Coordinator | Start | Finish | Project Name | Phase | Client | % Complete |
| 2008039 | Bruce | 1/15/2008 8:00 | 8/15/2008 17:00 | Multi Bldg (Cheny & DeGroat) Security Screens | Planning | 0% | |
| 1/15/2008 8:00 | 1/15/2008 17:00 | 1.Design | 0% | ||||
| 1/15/2008 8:00 | 1/15/2008 17:00 | 2.Bid | 0% | ||||
| 8/15/2008 8:00 | 8/15/2008 17:00 | 3.Construction | 0% | ||||
| 2007108 | Chris | 6/1/2007 8:00 | 8/15/2008 17:00 | Multi Bldg Brockway,DeGroat,Cheney Slate Roof Repairs | Design | 55% | |
| 6/1/2007 8:00 | 1/29/2008 17:00 | 1.Design | 100% | ||||
| 2/1/2008 8:00 | 5/15/2008 17:00 | 2.Bid | 0% | ||||
| 5/15/2008 8:00 | 8/15/2008 17:00 | 3.Construction | 0% | ||||
| 2008038 | Phil | 1/16/2008 8:00 | 8/15/2008 17:00 | Multi Bldg Higgins & Clark Secure Roof Access | Planning | 0% | |
| 1/16/2008 8:00 | 1/16/2008 17:00 | 1.Design | 0% | ||||
| 1/16/2008 8:00 | 1/16/2008 17:00 | 2.Bid | 0% | ||||
| 8/15/2008 8:00 | 8/15/2008 17:00 | 3.Construction | 0% | ||||
| 2008010 | Chris | 8/15/2007 8:00 | 10/30/2007 17:00 | Multi Bldg Install Defib Cabinets & Wiring | Complete | S.Meyers | 100% |
| 8/15/2007 8:00 | 8/15/2007 17:00 | 1.Design | 100% | ||||
| 8/15/2007 8:00 | 8/15/2007 17:00 | 2.Bid | 100% | ||||
| 8/15/2007 8:00 | 10/30/2007 17:00 | 3.Construction | 100% | ||||
| 2007103 | Chris | 6/1/2007 8:00 | 12/31/2008 17:00 | Multi Bldg Library & PER Retro-Commissioning | Design | 30% | |
| 6/1/2007 8:00 | 12/31/2008 17:00 | 1.Design | 90% | ||||
| 6/1/2007 8:00 | 12/31/2008 17:00 | 2.Bid | 0% | ||||
| 6/1/2007 8:00 | 12/31/2008 17:00 | 3.Construction | 0% | ||||
| 2008050 | Phil | 1/16/2008 8:00 | 8/15/2008 17:00 | Multi Bldg PER & Stadium Cameras Phase II | Planning | 0% | |
| 1/16/2008 8:00 | 1/16/2008 17:00 | 1.Design | 0% | ||||
| 1/16/2008 8:00 | 1/16/2008 17:00 | 2.Bid | 0% | ||||
| 8/15/2008 8:00 | 8/15/2008 17:00 | 3.Construction | 0% | ||||
| 2007110 | Chris | 6/1/2007 8:00 | 9/1/2008 17:00 | Multi Bldg RHD Stand Alone Heating/Cooling | Design | 3% | |
| 6/1/2007 8:00 | 7/15/2008 17:00 | 1.Design | 10% | ||||
| 6/1/2007 8:00 | 7/15/2008 17:00 | 2.Bid | 0% | ||||
| 6/1/2007 8:00 | 9/1/2008 17:00 | 3.Construction | 0% | ||||
| 200630 | Bruce | 12/29/2005 8:00 | 11/1/2007 17:00 | Multi Building Network Based Clocks | Const. | Bill Shaut | 99% |
| 12/29/2005 8:00 | 12/29/2005 17:00 | 1.Design | 100% | ||||
| 12/29/2006 8:00 | 12/29/2006 17:00 | 2.Bid | 100% | ||||
| 12/29/2006 8:00 | 11/1/2007 17:00 | 3.Construction | 99% | ||||
| 2008007 | Joe Wo | 8/1/2007 8:00 | 8/1/2008 17:00 | Multi Building Sandblast Yellow Painted Granite Curbs at Neubig, Corey, & Dowd | Constr | 1% | |
| 8/1/2007 8:00 | 8/1/2007 17:00 | 1.Design | 100% | ||||
| 8/1/2007 8:00 | 8/1/2007 17:00 | 2.Bid | 100% | ||||
| 8/1/2007 8:00 | 8/1/2008 17:00 | 3.Construction | 0% | ||||