200728 Joe Wo 10/16/2006 8:00 8/1/2008 17:00 Moffett Center Bus Stop Alterations Const Glenn Wright 100%
    10/16/2006 8:00 10/16/2006 17:00 1.Design     100%
    10/16/2006 8:00 10/16/2006 17:00 2.Bid     100%
    10/16/2006 8:00 8/1/2008 17:00 3.Construction     100%
2007117 TBD 5/8/2007 8:00 8/15/2007 17:00 Moffett Center Gym Electronic Floor Control Devices Hold G.Wright 0%
    5/8/2007 8:00 5/8/2007 17:00 1.Design     0%
    5/8/2007 8:00 5/8/2007 17:00 2.Bid     0%
    5/8/2007 8:00 8/15/2007 17:00 3.Construction     0%
200648 Joe We 6/1/2007 8:00 6/1/2009 17:00 Moffett Center Phase I Renovations Design R Kendrick 9%
    6/1/2007 8:00 2/15/2008 17:00 1.Design     21%
    3/31/2008 8:00 3/31/2008 17:00 2.Bid     0%
    6/2/2008 8:00 6/1/2009 17:00 3.Construction     0%