| Moffett Bldg. Projects - 01/08 | |||||||
| Project # | Coordinator | Start | Finish | Project Name | Phase | Client | % Complete |
| 200728 | Joe Wo | 10/16/2006 8:00 | 8/1/2008 17:00 | Moffett Center Bus Stop Alterations | Const | Glenn Wright | 100% |
| 10/16/2006 8:00 | 10/16/2006 17:00 | 1.Design | 100% | ||||
| 10/16/2006 8:00 | 10/16/2006 17:00 | 2.Bid | 100% | ||||
| 10/16/2006 8:00 | 8/1/2008 17:00 | 3.Construction | 100% | ||||
| 2007117 | TBD | 5/8/2007 8:00 | 8/15/2007 17:00 | Moffett Center Gym Electronic Floor Control Devices | Hold | G.Wright | 0% |
| 5/8/2007 8:00 | 5/8/2007 17:00 | 1.Design | 0% | ||||
| 5/8/2007 8:00 | 5/8/2007 17:00 | 2.Bid | 0% | ||||
| 5/8/2007 8:00 | 8/15/2007 17:00 | 3.Construction | 0% | ||||
| 200648 | Joe We | 6/1/2007 8:00 | 6/1/2009 17:00 | Moffett Center Phase I Renovations | Design | R Kendrick | 9% |
| 6/1/2007 8:00 | 2/15/2008 17:00 | 1.Design | 21% | ||||
| 3/31/2008 8:00 | 3/31/2008 17:00 | 2.Bid | 0% | ||||
| 6/2/2008 8:00 | 6/1/2009 17:00 | 3.Construction | 0% | ||||