| Memorial Library Project - 01/08 | |||||||
| Project # | Coordinator | Start | Finish | Project Name | Phase | Client | % Complete |
| 2008057 | Bruce | 1/15/2008 8:00 | 8/15/2008 17:00 | Memorial Libraary Commons Writing Center Add System Furniture | Planning | 0% | |
| 1/15/2008 8:00 | 1/15/2008 17:00 | 1.Design | 0% | ||||
| 1/15/2008 8:00 | 1/15/2008 17:00 | 2.Bid | 0% | ||||
| 8/15/2008 8:00 | 8/15/2008 17:00 | 3.Construction | 0% | ||||
| 200778 | Bruce | 3/7/2007 8:00 | 11/1/2007 17:00 | Memorial Library Card Access for Front Door | Complete | Gail Wood | 99% |
| 3/7/2007 8:00 | 3/7/2007 17:00 | 1.Design | 100% | ||||
| 3/7/2007 8:00 | 3/7/2007 17:00 | 2.Bid | 100% | ||||
| 3/7/2007 8:00 | 11/1/2007 17:00 | 3.Construction | 100% | ||||
| 2008055 | Bruce | 1/15/2008 8:00 | 8/15/2008 17:00 | Memorial Library Install New Blue Light at Bookmark Entrance | Planning | 0% | |
| 1/15/2008 8:00 | 1/15/2008 17:00 | 1.Design | 0% | ||||
| 1/15/2008 8:00 | 1/15/2008 17:00 | 2.Bid | 0% | ||||
| 8/15/2008 8:00 | 8/15/2008 17:00 | 3.Construction | 0% | ||||
| 2008023 | Bruce | 12/15/2007 8:00 | 2/15/2008 17:00 | Memorial Library Replace Back Entrance Glass Door | Constr | 67% | |
| 12/15/2007 8:00 | 12/17/2007 17:00 | 1.Design | 100% | ||||
| 12/15/2007 8:00 | 12/17/2007 17:00 | 2.Bid | 100% | ||||
| 2/15/2008 8:00 | 2/15/2008 17:00 | 3.Construction | 0% | ||||
| 200759 | Bruce | 2/1/2007 8:00 | 11/1/2007 17:00 | Memorial Library Replace West Main Entrance Doors | Constr | 99% | |
| 2/1/2007 8:00 | 8/15/2007 17:00 | 1.Design | 100% | ||||
| 2/1/2007 8:00 | 8/15/2007 17:00 | 2.Bid | 100% | ||||
| 2/1/2007 8:00 | 11/1/2007 17:00 | 3.Construction | 99% | ||||