| Dowd Fine Arts Projects - 01/08 | |||||||
| Project # | Coordinator | Start | Finish | Project Name | Phase | Client | % Complete |
| 2007113 | Bruce | 5/1/2007 8:00 | 11/30/2007 17:00 | Dowd Fine Arts Fall Protection Dowd Theatre | Complete | 100% | |
| 5/1/2007 8:00 | 5/1/2007 17:00 | 1.Design | 100% | ||||
| 5/1/2007 8:00 | 5/1/2007 17:00 | 2.Bid | 100% | ||||
| 5/1/2007 8:00 | 11/30/2007 17:00 | 3.Construction | 100% | ||||
| 200784 | Joe We | 3/7/2007 8:00 | 3/14/2008 17:00 | Dowd Fine Arts Graphics Art Silk Screen Sink | Planning | Lori Ellis | 56% |
| 3/7/2007 8:00 | 9/28/2007 17:00 | 1.Design | 100% | ||||
| 3/7/2007 8:00 | 11/30/2007 17:00 | 2.Bid | 100% | ||||
| 3/7/2007 8:00 | 3/14/2008 17:00 | 3.Construction | 0% | ||||
| 2008024 | Bruce | 11/15/2007 8:00 | 1/11/2008 17:00 | Dowd Fine Arts Green Room Carpet Replacement | Complete | 100% | |
| 11/15/2007 8:00 | 11/15/2007 17:00 | 1.Design | 100% | ||||
| 11/15/2007 8:00 | 11/15/2007 17:00 | 2.Bid | 100% | ||||
| 1/11/2008 8:00 | 1/11/2008 17:00 | 3.Construction | 100% | ||||
| 2008045 | Chris | 1/16/2008 8:00 | 8/15/2008 17:00 | Dowd Fine Arts Listening Room Renovation | Planning | 0% | |
| 1/16/2008 8:00 | 1/16/2008 17:00 | 1.Design | 0% | ||||
| 1/16/2008 8:00 | 1/16/2008 17:00 | 2.Bid | 0% | ||||
| 8/15/2008 8:00 | 8/15/2008 17:00 | 3.Construction | 0% | ||||
| 2008054 | Phil | 1/16/2008 8:00 | 8/15/2008 17:00 | Dowd Fine Arts TV Studio Lighting | Planning | 0% | |
| 1/16/2008 8:00 | 1/16/2008 17:00 | 1.Design | 0% | ||||
| 1/16/2008 8:00 | 1/16/2008 17:00 | 2.Bid | 0% | ||||
| 8/15/2008 8:00 | 8/15/2008 17:00 | 3.Construction | 0% | ||||