Bowers Hall Project - 01/08
Project # Coordinator Start Finish Project Name Phase Client % Complete
200797 Bruce 8/15/2007 8:00 10/25/2007 17:00 Bowers Hall Loading Dock Signage Complete J. Sternfeld 99%
    8/15/2007 8:00 8/15/2007 17:00 1.Design     100%
    8/15/2007 8:00 8/15/2007 17:00 2.Bid     100%
    8/15/2007 8:00 10/25/2007 17:00 3.Construction     100%
200625 Joe Wo 2/1/2007 8:00 11/1/2007 17:00 Bowers Hall Parking Lot Redesign Complete   100%
    2/1/2007 8:00 2/1/2007 17:00 1.Design     100%
    4/15/2007 8:00 4/16/2007 17:00 2.Bid     100%
    7/2/2007 8:00 11/1/2007 17:00 3.Construction     100%
2008027 Phil 12/20/2007 8:00 12/20/2007 17:00 Bowers Hall Rm 48 Asbestos Abatement Complete Twiss 100%
    12/20/2007 8:00 12/20/2007 17:00 1.Design     100%
    12/20/2007 8:00 12/20/2007 17:00 2.Bid     100%
    12/20/2007 8:00 12/20/2007 17:00 3.Construction     100%
2008051 Bruce 1/16/2008 8:00 8/15/2008 17:00 Bowers Hall Rm 339 New Stools Planning   0%
    1/16/2008 8:00 1/16/2008 17:00 1.Design     0%
    1/16/2008 8:00 1/16/2008 17:00 2.Bid     0%
    8/15/2008 8:00 8/15/2008 17:00 3.Construction     0%
2007118 Joe Wo 5/10/2007 8:00 9/1/2010 17:00 Bowers Hall Science Building Upgrade Planning   0%
    5/10/2007 8:00 8/15/2007 17:00 1.Design     0%
    8/3/2009 8:00 10/9/2009 17:00 2.Bid     0%
    10/9/2009 8:00 9/1/2010 17:00 3.Construction     0%